Air Permit Appplication for the East Aurora Compressor Station of National Fuel Gas Supply Corporation under CP11-128.
04/24/2011Sabine Pass Liquefaction, LLC Sabine Pass LNG, L.P. Liquefaction Project Resource Report 1 General Project Description CP11-___-000 January 2011 -i- January 2011 Liquefaction Project Resource Report 1 TABLE OF CONTENTS Section Page No. 1.0 PROJECT DESCRIPTION ................................................................................................................ 1 1.1 INTRODUCTION .............................................................................................................................. 1 1.2 PROPOSED FACILITIES ................................................................................................................. 2 1.2.1 Liquefaction Project Stage 1 ................................................................................................. 2 1.2.1.1 LNG Trains 1 and 2 ............................................................................................... 2 1.2.1.2 Other Infrastructure and Modifications, Stage 1.................................................... 5 1.2.1.3 Modifications to Existing SPLNG Facilities, Stage 1 ........................................... 5 1.2.1.4 New Buildings, Stage 1 ......................................................................................... 6 1.2.1.5 Marine Terminal and LNG Transfer Lines ............................................................ 6 1.2.1.6 LNG Storage .......................................................................................................... 6 1.2.1.7 LNG Vaporization/Natural Gas Sendout ............................................................... 7 1.2.1.8 LNG Impoundments .............................................................................................. 7 1.2.2 Liquefaction Project Stage 2 ................................................................................................. 7 1.2.2.1 LNG Trains 3 and 4 ............................................................................................... 7 1.2.2.2 Other Infrastructure and Modifications, Stage 2.................................................... 8 1.3 PURPOSE AND NEED ..................................................................................................................... 8 1.3.1 Department of Army Permitting: Basic and Overall Project Purpose ................................... 9 1.3.1.1 Basic Project Purpose (Water Dependency) .......................................................... 9 1.3.1.2 Overall Project Purpose ......................................................................................... 9 1.4 LOCATION AND DESCRIPTION OF PROJECT ......................................................................... 10 1.4.1 Liquefaction Facilities (LNG Train).................................................................................... 11 1.4.2 Additional Facilities ............................................................................................................ 11 1.5 LAND REQUIREMENTS ......................................