Trunkline LNG Company, LLC/Trunkline LNG Export, LLC submit its Application for Authorization Under Section 3 of the Natural Gas Act for the proposed Lake Charles Liquefaction Project, under CP14-120.
March 25, 2014
Page 2
March 25, 2014
Ms. Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
888 First Street, NE
Washington, DC 20426
RE: Trunkline LNG Export, LLC and Trunkline LNG Company, LLC
Liquefaction Project
Docket No. CP14-___-000
Application for Authorization Under Section 3 of the Natural Gas Act
Dear Ms. Bose:
Pursuant to Section 3 of the Natural Gas Act, as amended (NGA), 15 U.S.C.
717f(b)(a)(2013), and in accordance with Parts 153 and 380 of the Federal Energy Regulatory
Commissions (Commission) Regulations, 18 C.F.R. Parts 153 and 380 (2013), Trunkline LNG
Export, LLC (TLNG Export) and Trunkline LNG Company, LLC (TLNG and, collectively,
Applicants) submits herewith for filing an application for authorization (i) to site, construct, own and
operate new liquefaction facilities (Liquefaction Facilities) on a site adjacent to TLNGs existing
liquefied natural gas (LNG) terminal located near Lakes Charles, Louisiana in Calcasieu Parish; and
(ii) to construct, own and operate minor facility modifications at the Trunkline LNG Terminal to
facilitate the storage and subsequent export of the LNG (Modified Facilities). The Liquefaction
Facilities and the Modified Facilities are collectively referred to as the Liquefaction Project.
The Exhibit F (Environmental Report), as part of the Application, is a combined report of
Applicants proposed Liquefaction Project and Trunkline Gas Companys proposed Pipeline
Modification Project being filed concurrently with this application.
Applicants have organized the information being filed as follows:
PUBLIC Transmittal Letter, Application Volume (includes Form of Notice for the
Federal Register, Exhibits A through E-1, G, H and Z.
Exhibit F Environmental Report
o PUBLIC Public version of Resource Reports 1 through 13 including
Narrative Text, Tables, Figures and Appendices
o PRIVILEGED Privileged version of Resource Reports 1,4,11 and 13
including Narrative Text and Appendices (Privileged Information Do Not
Release)
1300 Main Street | Houston, Texas 77002 | (713) 989-7000
March 25, 2014
Page 2
o CEII CEII version of Resource Reports 1, 9, 11 and 13 including
Appendices and Plot Plans (Critical Energy Infrastructure Information
Do Not Release)
In conjunction with FERC Staff comments to Applicants Draft Resource Reports 1 through 13
received on September 27, 2013, February 19, 2014, and March 11, 2014, respectively in Docket No.
PF12-8-000, FERC Staff requested a matrix identifying the specific locations in the resource reports
where the information requested pursuant to their comments could be found in the Resource Reports
being submitted with this application. Applicants are hereby submitting the requested matrix as an
attachment with this filing.
Any questions concerning this filing should be addressed to the undersigned at (713) 989-2024.
Respectfully,
TRUNKLINE LNG EXPORT, LLC
TRUNKLINE LNG COMPANY, LLC
/...